I need to create an exportable report that displays individual issue age based on the "change start date" that is selected for each. Any suggestions or prebuild reports that I could use to accomplish this?
Hello @Jordon Martig
Welcome to the community.
Is "change start date" a custom field that you have added to your issues?
One solution would be:
1. create another custom field named "age"
2. use an automation to set that field every time "change start date" is changed
3. use the issue search screen to retrieve the issues
4. set the output display to list view and include the "age" field in the columns
5. export the results.
It may be a custom field. It was available to me when creating this project. I'll give this a try and see how it works. thanks!
@Trudy P Claspill
I've got the custom field "age" added to my screen, but am stuck on the automation. I'd like the field age to count the days since the date selected in "Change start date." Any insight on how to accomplish this?
What have you got for your automation so far?
You'll need a trigger. I would select Field Value Changed and then pick you "Change start date" field.
Then you are going to need an Action. I would pick Edit Issue.
Pick the field you want to edit - "age".
You are going to need to use smart values to figure out the date difference between now() and the date in your custom field. This is a starting point for learning about smart values:
https://support.atlassian.com/cloud-automation/docs/what-are-smart-values/
And here is a page about working with smart values for dates and time. You should look at the "diff" function for getting the difference between two dates.
https://support.atlassian.com/cloud-automation/docs/jira-smart-values-date-and-time/
Hello @Jordon Martig ,
If you are OK with using a marketplace app for this, our team at OBSS built Timepiece - Time in Status for Jira for this need. It is available for Jira Server, Cloud, and Data Center.
Time in Status mainly allows you to see how much time each issue spent on each status and on each assignee.
The app has Consolidated Columns feature. This feature allows you to combine the duration for multiple statuses into a single column and exclude unwanted ones. It is the most flexible way to get any measurement you might want. Measurements like Issue Age, Cycle Time, Lead Time, Resolution Time etc.
Instead of working based on a given date, the app can display each status duration separately. This way, you move the issue to a "work started" status (or an equivalent status in your workflow) when the work actually starts and ignore the times before that.
For all numeric report types, you can calculate averages and sums of those durations grouped by the issue fields you select. For example total in-progress time per customer (organization) or average resolution time per sprint, week, month, issuetype, request type, etc. The ability to group by parts of dates (year, month, week, day, hour) or sprints is particularly useful here since it allows you to compare different time periods or see the trend.
The app calculates its reports using already existing Jira issue histories so when you install the app, you don't need to add anything to your issue workflows and you can get reports on your past issues as well. It supports both Company Managed and Team Managed projects.
Time in Status reports can be accessed through its own reporting page, dashboard gadgets, and issue view screen tabs. All these options can provide both calculated data tables and charts.
And the app has a REST API so you can get the reports from Jira UI or via REST.
Using Time in Status you can:
Timepiece - Time in Status for Jira
EmreT
Hi @Jordon Martig
As an alternative, you can try Status Time Reports app developed by our team. It mainly provides reports and gadgets based on how much time passed in each status.
Here is the online demo link, you can see it in action and try without installing the app.
If you are looking for a free solution, you can try the limited version Status Time Free.
Note: If you are interested in cycle and lead time, you can have a look at the article below.
Cycle Time and Lead Time in Jira: Productivity Measurement with Two Critical Parameters
Hope it helps.
If you are fine with a mktplace app, for a readymade solution, you can try out our add-on to get this data.
The "Time in Status" report shows the time the issue was in each stage of its lifecycle.
Time in Status Reports
The main features are as below
Hello All,
In any case, if you want to measure aging of the status. I came across this app which gives analysis of how long tasks remained in each Jira status, also tracks involved users, and this will help to increase team efficiency.
Thank you,Amit Ajmera