I'm trying to set up an Advanced Roadmap. I've created a hierarchy where we have
Goal -> Initiative -> Epic -> Task
I've added the `Progress (issue count)` field to track the progress. However, it's not rolling up as I expected. I can see the progress of every Task under an Epic, but when I get to Initiative, it only shows the progress of the Epics. By the time I get up to the Goals, it looks like nothing is happening, even though half of the tasks are complete (because no Initiative as a whole is finished yet).
Is there a way to keep rolling up (summing) the number of issues contained within each hierarchical level? So that I can see the total progress on issues within every subsequent level and not just the progress of the next level?

Thanks in advance!