I need to set a fixed date for a couple of issues in JIRA Portfolio 2. This is because I need more control over when a issue is done so other issues that are blocked do not move.
So in a way I want some issues 'pinned' in the schedule. In Portfolio 1 we had the option to set a "Fixed date" as an issue deadline, but the option is removed in version 2. Now my whole planning is screwed because of 1 item that is behind schedule. I need to count on the deadlines for some issues, not on the deadline of the whole version.
Is there anyone with a solution or work-around to this problem? If i need to be more clear, please let me know! 