Hi community,
The basic velocity chart shows me 3 major things:
Commitment (initial and final) + Completed work.
How can I reflect on the time spent on a task that's not completed yet?
I mean, if an issue was estimated by 10h and currently 7h was already spent working on it - the velocity chart will show me 10h in the commitment and 0h in the completed work.
This situation doesn't reflect the real situation and looks like no effort was invested in favor of this task until it will fully be completed.
Thanks,
Dean