Hey Guys,
I have many tasks in my roadmap but only 7 tasks are assigned to my Sprint-1How is it possible to add more of them to sprint-1 ?
Thank you for any help
Hi @Sandro Lainer ,
welcome to the Atlassian community!
Could you try to add Sprint field to your plan view? You should be able to select sprint for each issue in your list.
Hope this helps,
Fabio
Hello @Sandro Lainer,
You can drag and drop the issues from your backlog into the Sprint-1 or you can edit the "sprint" field to select the sprint value. Both options will help you to add the desired issues into the sprint.
Hope this helps!
Thanks!
It looks like you're new here. Sign in or register to get started.