When attempting to pull together some metrics per sprint, I have noticed an anomaly with the source of the data Jira is using for reports.
Example - Sprint 9:
From the Sprint report (in story points)
- 187 completed
- 70 not completed
Total story points 257
From the Velocity chart
- Commitment - 220
- Completed - 187
Why is there a difference in story points between the sum of completed and not completed (257) and the commitment (220) ?
Where does Jira pull its data sources from for these reports?