Hello togehter,
when I add multiple dependencies to a, for example task, because this task is going into multiple milestones, the end date will be set to latest milestone instead of the earliest milestone.
In Microsoft project I could choose from where it should be calculated. In WBS I didn't found such an option.
Is there a option that I missed or is it still not working.
best regards
Tom