Hello,
I am working in Advanced Road Maps where individual engineers each have boards and then one board combines all of their work and lays it out in a "manager" view. Each "Team" is one engineer. Each "Epic" is a product job that will be manufactured. The "Tasks" that fall beneath each "Epic" are the actions required of up to three different engineers.
The issue we are encountering is that the "peer review" task being done by a second engineer are not scheduled sequentially, but instead fall at the end of all other "Epics" / "Tasks" assigned to the secondary engineer. This results in large scheduling gaps for each "Epic" and does not allow Jira to match our workflow.
How do we ensure all of the tasks that fall under each "Epic" are aligned sequentially, especially when multiple teams will be splitting the "Tasks" workload?