We are trying to use Jira Cloud to project when a project milestone will be finished. We are looking at the Version Report reports. (BTW, we are running 2-week sprints)
The version report shows our predicted completion date as 7/14/22. However, we predicted we'll finish mid- to late December.
Some additional information:
* 5.06% of the version is unestimated.
* We have 644 points incomplete.
* Our 4-sprint average velocity is 55.25.
Just using those numbers, we can estimate our completion date late September. However, we have some dependencies and limited skill availability, so it got pushed to December. But why is there such a difference between what Jira estimates and what we estimate.
Additionally, I've never seen a burn-up chart go up sharply from today's date like this one..

Any insight is appreciated it. TIA!