I have a business project made with the help of Jira Work Manager, there is one board without sprints, so there are a lot of completed tasks in the "Done" column, is there any option that can take them from there (except the filter).
Hi @Ivan Andrieiev ,
I think you you can use the release button as a simple way. It is on the top right of the board and will create a release and add all issues in the done column. This will then remove the issues.
Hi @Ivan Andrieiev
Unfortunately, for Business projects (i.e. Jira Work Management projects) you cannot do releases or manually remove the Done issues. They will disappear from your board after 2 weeks.
If you desire this functionality, you should click on the Give Feedback button on the bottom left and let them know.
Hi @John Funk , If they disappeared after two weeks it would be normal, but they remain. Maybe I need to make changes to the project settings?
No, that's not something you can do. So this is on the built-in board that comes with the JWM project? Or did you create another board?
@John Funk
I didn't create a new board, it's all happening on the board that was created with the project. Will the tasks stay there forever?