My "Not started/In Progress/Done" bubbles are not reflecting exactly what is going on. It currently shows 124 story points Not started, 0 In progress, and 18 Done. This is wrong.
First issue, before I clicked "Start sprint," it showed a total of 180 story points for this sprint backlog. In fact, the burndown chart reflects the correct total of 180 as well. Why do the bubbles not properly account for the total anymore?
Secondly, there are MANY stories (or parent tasks) currently In progress...this is shown correctly on the scrum board screen columns, and also on the actual story tasks. IE...story 1563 has 13 story points and it's current status is "In progress." Why is this not reflecting on the bubbles?
I also want to point out that we are NOT estimating on the sub-tasks (or acceptance criteria), we are ONLY estimating story points on the parent task, otherwise known as the Story.
I've attached some screens.
Screen 1: 1) Shows 0 story points In progress. 2) Total story points = 142, there are 180 total in this sprint (shown in screen 3)
image2015-3-5 10:6:25.png
Screen 2: Clearly shows one of the items below as In progress, with 5 story points associated. This is NOT reflected in Screen 1 bubble.
image2015-3-5 10:10:7.png
Screen 3: Burndown chart clearly shows 180 total story points in this sprint. But screen 1 shows 142 total because it is NOT reflecting In progress.
image2015-3-5 10:11:22.png
Thanks,
Tony