Hi!
We recently started using Jira Plans for our sprint and capacity management.
We have encountered a behavior which we do not understand and was wondering if anyone could tell me, whether this is intended and what the reasoning behind it is.
We created a Team called "Anna & Stefan" with a capacity of 10d per sprint. A sprint lasts for 2 weeks. I then created a Story with 15d original estimate to be completed over 2 sprints. My expectation would be, that the story would fill up the first sprint fully (10/10 days) and the second sprint only halfway (5/10 days). However it does the exact opposite:

Is this intended? If I increase the original estimate to 16d, it even shows the last sprint as red and overbooked instead of assuming a load of 6 days for the first sprint.

Thank you!