We created a scrum (entreprise-managed) project; and our roadmap is showing the sprints timeline.
Can we switch it to a normal timeline view and how?
Thank you!
Hi @Amel LAOUINI
Do you mean the roadmap works as per this help page?
If yes, as far as I know you can't deactivate this feature on the basic roadmap - aside from removing all the Start/End dates from future sprints, which will clear them.
Or you can change to a Kanban Board, where these roadmap settings are not relevant.