I am managing JIRA projects which contain tasks and bugs for Hardware as well as software, for SW, implemented means the new fix or new sw is in place and will be further verified, now for hardware, after the task is assigned there is a large amount of work done before is considered implemented, should I move the task / bug to Implemented based on the % of work done for the task/bug or should I keep the task/ bug work at "assigned" until the hw solution has been completed? This is the flow I have assigned in my projects:
Open -> Assigned -> Implemented -> Verified -> tested -> closed
The problem I have with HW tasks is that they stuck in "Assigned" for long time, this is translated as " No progress" by management. Any suggestion or recommendation is greatly appreciated. Thanks.