How I can edit sprint on subtasks? user stories always don't complete during 1 sprint.
Hi @fariba_peyhani ,
Sub-task inherit the sprint from the parent. You can't have different sprint for the sub-task(s).
Hi @Sreenivasaraju P, Thanks.
Yes, I agree. What we can do with our user stories?
they are in progress, semi subtasks are done.
Hi,
Either you have to complete all sub-tasks in the same sprint or move the complete story to next sprint.