Hello,
I have a task "A" that starts on March 1, 2022, and ends on March 5th, 2022. This task is a predecessor of task "B" which starts on March 10, 2022. The lag time is 5 days between the tasks.
Now the puzzle starts... When I change the start date of Task "A" from March 1 to March 8th the start date for task "B" remains the same BUT it should be automatically be updated to March 13th.
Please, explain to me what I am doing wrong
Thank you in advance