Hi!
We have a task with a estimate effort of 40 hours and we have estimated the start date. BigPicucture has estimate the end date using 8 hours each day instead of the resource workload schedule that is 9 hours through Monday - Thursday and 6h 30 min on Fridays.
How can we configure BigPicture to use the resource workload schedule for the estimate end date of a task?