Is there any way each task associated to an Epic shows its time bar on the Roadmap section?
Currently only appears the timebar for the Epic card itself but not for the Tasks inside that epic:
Hi @Nacho García-Robledo
This is the limitation of the basic project specific roadmap. You would need to either use Advanced Roadmap (Jira Premium plan) or use an app like BigPicture.
I hope it helps.
Ravi
Or, like Structure.Gantt You can use this link (or create your own) @Nacho García-Robledo to check out more options:https://marketplace.atlassian.com/addons/app/jira/cloud-fortified?hosting=cloud&moreFilters=vendorSupported&query=gantt
Thanks @Ravi Sagar _Sparxsys_ & @Dave Rosenlund _Trundl_ !
Unfortunately both options require further investment so for the moment I think there is no free option to cover this demand.
Nevertheless, I appreciate your answers!