Hi,
I have this problem and I don't really know how to solve it.
We are using JIRA+BigPicture for organization and scheduling.
We have the structure organized in such a way that JIRA projects aggregate the work of teams (e.g. projects: android, ios, server, bigdata...). In projects, tasks are added for teams and labeled accordingly. Then, proper projects are created in BigPicture that pull specific tasks from individual JIRA projects (e.g., project prog-1 pulls all tasks with label prog-1).
QA-we have them organized in such a way that they are part of the workflow. The developer finishes the job and by changing the status passes it to the tester within the same project and workflow and here is the crux of the problem.
The problem is that the task is one and it is done by two people (programmer and tester). The estimate includes the work of the programmer and the tester. Problems:
- in BigPicture we see the workload of the person who is currently assigned (so the programmer is loaded with the time scheduled for the tester)
- as it is one assignment, so the tests are in the same block. You cannot, for example, start scheduling them for a few days later.
How do you solve this in your projects?