Say, as part of the basic roadmap planning, I create a user story which I want to start on 3/1/22 and end on 10/1/22. So, I set the start date and due date fields to 3/1/22 and 10/1/22 for that particular user story.
I create a 1 week sprint on 6/1/22 and add the user story to it. Then I start the sprint. The user story status is changed from 'TO DO' to 'IN PROGRESS' on 6/1/22 and from 'IN PROGRESS' to 'DONE' on 12/1/22. I then close the sprint on 13/1/22 since it was a 1 week sprint.
My question is -
1. I want to now see the actual start date (6/1/22) and actual end date (12/1/22) for the user story. In which fields are these dates recorded?