I need to show which Epics the team have worked on over the quarter and a ratio across them.
I've written a filter to show issues closed during last quarter:
project in (ProjectX) AND issuetype in (story, bug, spike, task, analysis) AND status changed to (Resolved, Done) before "2022/01/01" after "2021/09/30"
The epics in this project have the story points calculated using automation.
So I have the time period, I have the points in the Epics, now I just need to show the breakdown. Eg: We completed 40 points in Epic-123 and 20 points in Epic-456.
I created a dashboard and the standard Pie Chart would be perfect... except that shows issues, not points. The Workload Pie would also work if they had Story Points in 'Time field to report on'.
Any other ways to do it?