We use story swimlanes in our sprint boards with subtasks being moved throughout each column.
Sometimes stories aren't completed in a sprint and this means the sprint board can get cluttered with subtasks that were already completed in previous sprint.
We would like to create a quick filter to be able to easily hide subtasks completed in the previous sprint.
I attempted the following solution
- Added a custom Text Field (single line) named "Done Sprint"
- Set the text field to the active sprint name via a jira automation when the subtask is transitioned to done
- Tried to add this quick filter: "Done Sprint" IS EMPTY OR "Done Sprint" IN openSprints()"
This last step outputs the following error:
The operator 'in' is not supported by the 'Done Sprint' field. |
What is the quick filter query I should use in this case (assuming such a query is actually doable)? Would there be any other way to have the option not to display subtasks completed in previous sprints on the sprint board?