Hi!
We have a problem with unresolved issues disappearing from the scrum board after a sprint is closed.
Details:
In our project, developers are moving issues from status "open" (via some other stati) to "testing" (status category "In Progress"), after which our testers take over and set its status to "done" (status category "Done").
As the project is large, the devs don't want 50 or more issues per sprint in the "done" column, so they removed it => the rightmost colum is now the one with status "testing".
The weird thing is, if they complete the sprint, all issues in the "testing" status/column are marked as "Completed" in the sprint report and disappear from the backlog.
==> How does Jira mark those issues as "completed"? Which field am i missing?
It's not resolution nor status nor the status category. The sprint field can also be empty as backlog issues do have an empty sprint field...
And the other question is: Why is jira determining issue completion upon "active sprint board column" rather than than "status category" or "resolution"?