I'm trying to determine if my Sprint deadlines are realistic. I have assigned resources and estimated hours (days) to all tasks. Can I get Jira to lay this out in Roadmaps (like a Gantt Chart) showing the tasks being done in order and respecting the dependencies?
When I look at the Roadmap now it just makes each task the entire length of the Sprint.