Hi everyone,
I am trying to grow my JIRA knowledge and I hope you can help.
This is the scenario:
Story 1
Start Date: Jan 1 2021
End Date: Jan 2 2021
Story 2
Start Date: Jan 3 2021
Start Date: Jan 4 2021
Questions:
1. How do I quickly link stories instead of manually opening each story and creating links?
2. How do I prevent date overlaps?
If I change the start/end date of Story 1, I want Story 2 to adjust automatically so they don't overlap.
I tried this automation but it doesn't seem to work.
I tried this but it's not working:
https://www.atlassian.com/software/jira/automation-template-library#/rule/1357113/25938353