Hello,
Velocity Chart - Commitment not showing on my first sprint. Please suggest
We did change the estimates on the first sprint - I believe that could be the reason.
any other information will be helpful.
Harpreet
Hi @Harpreet Singh -- Welcome to the Atlassian Community!
When you started the sprint (date/time) were the stories sized with story points? If not, the total was zero (0) at the time the sprint started, and so was the "commitment" for the report.
In that case, a tip is to complete your sprint planning/sizing before starting the sprint in Jira.
Kind regards,Bill