Hello,
I've noticed a strange issue where tickets in our Sprint, despite being Closed and Resolved during the Sprint, continue to be rolled over to the next Sprint. When i look at the Sprint Report, it suggests that the Issue wasn't completed in this Sprint, and show a status that's considered incomplete/unresolved for the affected tickets.
However, i've been absolutely making sure to Close these tickets (and marking them as Resolved) prior to Sprint closing. Looking at the Ticket details and history confirms this, yet they consistently move over to the next Sprint. Please see images below:




As the pictures above suggests, this behavior affected us for the last 4 Sprints, but we haven't made any changes to board settings or project configurations that coincides with this time.
You can see all these tickets show up as `Verify in Production` in the Sprint report, but looking into the ticket history for all of these tickets always shows that the Resolution was set to DONE, and status was changed to CLOSED, prior to closing the Sprint. However, when the Sprint is closed, the ticket is then added to the next Sprint.
I've also worked with other Projects/Boards with this exact same configuration and process within the same organization, dozens of times without issues, so at this point this feels more like a Jira bug...
Any ideas what's going on here?