We are currently planning the project on Advanced Roadmap. I am looking for a way to use auto-scheduling based on the dependencies.
My tickets (Tasks) have estimates but no Start and Due Dates yet, since I expect to get those from the Auto-Scheduling process. As a result, there are no bars on the roadmap plan, which means that I cannot create dependencies of the AR Plan.
So unless I will go out of the Plan and create the dependencies on the tickets, I will not be able to get the Auto-Scheduling working.
Is there a way to get plot the dependencies on the Plan without the Start/Due dates set, as this is the point of using Auto-Scheduling?