Hello,
I am new to Jira and am looking for some insight.
I am looking to use automations to help with rescheduling issue dependencies.
My ideal workflow I am trying to achieve is as follows:
- Due date for task A is moved 5 days out
- Start date and due date for linked task B is moved out by 5 days
Ideally I want task B to move by how ever many days I moved task A by. So far I have only been able to move the due date by a standard timeframe (ie {{issue.startDate.plusDays(7)}}). The automation for the start date removes the start date all together. I am not sure what I have done wrong. I have attached a screen shot of how my rule is currently set up.
Any suggestions are appreciated.