How add subtask to Backlog in team-managed project
Hello, @Ricardo Cunha . You can add task to the backlog and then viewing subtask in the Sprint, but The proper issue to be added to the backlog is task, history, epic...
Sub-tasks are not sprint-able items, they are entirely a part of their containing issue. They do not get seen in backlogs because there's no point - even if you did display them, they aren't going to go into the sprint as anything other than as a part of their container, and you can't rank them outside their containing issue. They add nothing to what the backlog is for - refinement and deciding what issues go into the sprint.
It looks like you're new here. Sign in or register to get started.