Dear Jira Community,
I am not sure if this was already asked here before. One of the teams that I am currently supporting often works on new feature issues and later rolls it out to other countries. The complexity is rather low but rolling out to other countries still takes quite a lot of time. Thus, I would like to ask you how should the team estimate the issues for the other countries.
For example, the first issue has 13 story points. The other issues to roll out to other countries in terms of complexity could have 2, for example, but are still going to take a day to complete. This can mislead the team's velocity.
What are the best practices in this case?
Thank you very much in advance!