There are three green readiness statuses in an agile project workflow. Done, outdated, and canceled.
After the sprint is closed, tasks in the "green" status "done" or "canceled" are not considered closed. When trying to complete a sprint in these statuses, Jira says that these tasks have not been completed. She then suggests moving all of these tasks into a new sprint.
But, if I select the "outdated" status, then the tasks are considered closed and are transferred correctly.
What is not working correctly? How do make it so that the tasks are transferred correctly in any "green" statuses? Thanks