Good afternoon.
how do I always leave the deadline at a certain number of days from the start date?I'm using {{startDate.plusDay(2)}} but it's not working.
Can you provide more information?
Is this part of an Automation rule? If so, can you show us the rule? And what information is provided in the Audit Log for the rule?
hi @Trudy P Claspill is the rule wich i used
It appears that your rule is intended to modify the Start Date and Due Date on sub-tasks when the Start Date on a parent task is changed. Is that correct?
How is your rule not working? Is Due Date not getting changed at all, or is it getting changed to an unexpected value?
The Due Date field is being set based on the value of the Start Date field in the subtask. What code are you using to se the subtask Start Date field? Is that working?
What does the Audit Log for this rule say when the rule is executed?
- Correct.
- Not work, the Due Date not getting changed.
- The same of parent issue, it's work.
- The audit log presents "sucess", don't detect bugs.