I am trying to replicate MS Project schedule modeling ability in Jira. I figured out how to have a ticket's start move to be 1 business days after the blocker's due date:
IF trigger issue due date changes
THEN for blocks start date set to: {{triggerissue.duedate.plusBusinessDays(1)}}
That works well!
But now I want the due date on the destination issue to be the field change to the start date of the destination issue caused by the above. I can't figure out what to put in?
So I currently have:
IF trigger issue due date changes
THEN for blocks: started date set to {{triggerissue.duedate.plusBusinessDays(1)}}
AND due date set to {{targetissue.startdate.fieldchange}}
The last bit just empties out the due date field! Why? What am I doing wrong?