Typically when I use Jira, the customer wants sprints/backlog in that and then the timeline is in some other tool like Smartsheet. In this case, they want to use your roadmap. So I read up on it and enabled it. I'm trying to figure out how I get it so that Epic B (Planning) doesn't start till Epic A (Initiation) is done. I know I probably have to put dates on the issues (they are stories, not tasks) and maybe say that the first issue in Planning (or the epic) is blocked by the first Epic. Or do I have to create a taskboard first? A little confused here. So rather than the second epic being directly under, it would show it starting on completion of the first