I have a Parent Story with Time estimate 3d. This was broken down into 3 subtasks and those were given 1 day each. Now the Time Tracking is indicating that we have 1w 1d remaining which is correct given 3d in parent and 1d x 3 sub tasks.
I have edited the parent to 0d and ticked the Include Sub Tasks box but still time remaining is 1w 1d.
Time remaining should be 3d as no work has been started. How can I change Time Remaining to reflect properly?