Using the data set below I'm unable to get epics, tasks, and subtasks linked together during import to a next gen board. I'm getting no warnings or errors and everything imports.
However:
1. I cannot see subtasks linked to tasks
2. I cannot see tasks linked to epics
3. and since subtasks are not linked to tasks i cannot see subtasks at all in the next gen board and only through filtering.
Very frustrating and time consuming if anyone can assist i would greatly appreciate it!
| Epic Name | Epic Link | Parent Id | Issue Id | Issue Type | Summary | Due Date | Start Date |
| Contract Transfers | | | | Epic | Contract Transfers | 1/31/2022 | 3/2/2022 |
| | Contract Transfers | | 101 | Task | Copier Contracts | 12/15/2021 | 1/14/2022 |
| | | 101 | 1011 | Sub-task | Identify/Validate list of copiers by division | 9/1/2021 | 10/1/2021 |
| | | 101 | 1012 | Sub-task | Work with Ricoh to transfer billing | 12/15/2021 | 1/14/2022 |
| | Contract Transfers | | 102 | Task | Data Circuit Contracts | 11/1/2021 | 12/1/2021 |
| | | 102 | 1021 | Sub-task | Identify/Validate list of data circuits | 9/1/2021 | 10/1/2021 |
| | | 102 | 1022 | Sub-task | Contact Carrier to request change of owner form | 10/1/2021 | 10/31/2021 |
| | | 102 | 1023 | Sub-task | Submit owner change form to carriers | 11/1/2021 | 12/1/2021 |
| | Contract Transfers | | 103 | Task | Ring Central account | 12/15/2021 | 1/14/2022 |
| | | 103 | 1031 | Sub-task | Discuss transition of configuration to QUES account | 9/1/2021 | 10/1/2021 |
| | | 103 | 1032 | Sub-task | Engage Ring Central to assist with moves | 9/15/2021 | 10/15/2021 |
| | | 103 | 1033 | Sub-task | Review and sign RC SOW | 10/1/2021 | 10/31/2021 |
| | | 103 | 1034 | Sub-task | Complete transition of RC accounts | 12/15/2021 | 1/14/2022 |
| | Contract Transfers | | 104 | Task | Security Systems | 12/15/2021 | 1/14/2022 |
| | | 104 | 1041 | Sub-task | TotalConnect Security Systems | 10/1/2021 | 10/31/2021 |
| | | 104 | 1042 | Sub-task | Create new contract and account with Total Connect | 12/1/2021 | 12/31/2021 |
| | | 104 | 1043 | Sub-task | Migrate services to new contract | 12/15/2021 | 1/14/2022 |
| | Contract Transfers | | 105 | Task | Mobile Solutions | 12/15/2021 | 1/14/2022 |
| | | 105 | 1051 | Sub-task | Identify mobile devices that need to be transitioned | 12/1/2021 | 12/31/2021 |
| | | 105 | 1052 | Sub-task | Have Mobile Solutions create a new bucket | 11/1/2021 | 12/1/2021 |
| | | 105 | 1053 | Sub-task | Submit list of phone numbers to M.S. to move | 12/15/2021 | 1/14/2022 |
| | Contract Transfers | | 199 | Task | Post Transition Cleanup/Validation | 1/31/2022 | 3/2/2022 |
| | | 199 | 1991 | Sub-task | Validate transition of Mobile Solutions accounts | 1/31/2022 | 3/2/2022 |
| | | 199 | 1992 | Sub-task | Validate billing of Security Systems | 1/31/2022 | 3/2/2022 |
| | | 199 | 1993 | Sub-task | Validate billing of Ring Central account | 1/31/2022 | 3/2/2022 |
| | | 199 | 1994 | Sub-task | Validate billing of Data circuits | 1/31/2022 | 3/2/2022 |
| | | 199 | 1995 | Sub-task | Validate billing of copiers | 1/31/2022 | 3/2/2022 |
| Active Directory | | | | Epic | Active Directory | 1/31/2022 | 3/2/2022 |
| | Active Directory | | 201 | Task | AD OU Structure | 8/31/2021 | 9/30/2021 |
| | | 201 | 2011 | Sub-task | Contact IT for OU Architecture | 8/1/2021 | 8/31/2021 |
| | | 201 | 2012 | Sub-task | Define dual OU Architecture | 8/15/2021 | 9/14/2021 |
| | | 201 | 2013 | Sub-task | build out OU Architecture | 8/31/2021 | 9/30/2021 |