we have this for more than a week now, "We can't create the subtask"
on every user story in the project.
Hello @Luuk Ebenau ,
please check the below.
1. does the user have "create issue" permission in the project.
2. check if any condition is applied on "create transition" for sub-task workflow.
Thanks.
Anvesh
I found the issue, there was a field made required on user stories (timeregistration)
this apprently made stories and subtasks fail with non-sensical error messages
Thanks!