I would like to see previous completed sprints. However, I do not have the Sprint Reports as an option. I am using the Next-Gen version. Help.
Thank you.
You have to enable Reports in Project Settings > Features.
Thank you for your reply. It has already been enabled and I am still not seeing "Sprint Report" I only get the following 4 reports:
If you are talking about the "Sprint Report" that is available in Company Managed projects, the equivalent for Team Managed projects is the "Sprint burndown chart"