Hello,
Is it possible to add Start dates and End Dates to Child Issues that are under Epics?
Thank you,
Johnathon Sisounthone
Hi @Johnathon Sisounthone
Yes, you may do that. The field names are Start Date and Due Date.
You could set those fields manually by putting them on your edit views, or update them automatically with automation rules, workflow, or scripting. For some users, they cascade the values from the parent down to the children, and for others they do the opposite, rolling them up to the parent epic.
Best regards,
Bill
Hi @Bill Sheboy
Thank you. Is there a way to make the dates appear on my roadmap? The only dates that I am able to see on the roadmaps are Parent Epics.
Kind regards,
Johnathon
Not yet for the basic roadmaps, as with the standard version of Jira. I believe their is a suggestion to make these visible for the child issues.
Is there another version of Roadmaps that would show the time bars of Child issues on the chart?