Hello Atlassian Community!
My conundrum -
Different reports on same Sprint show different point totals. Some issues are in the Sprint, but not showing up in any report or list from a report.
Examples -
Backlog view of the current Sprint has 68 points
Burndown chart shows only total of 50 points
Burnup chart showed 42 points
Sprint Report shows sections as Completed 11/Not completed 31/Completed outside of this Sprint 26
--- for a total of 68 points
I believe I understand all of the numbers except for the Burndown chart holding 50 vs the Burnup holding 42. What am I missing?