Hi guys,
I'm trying to use the Structure Gantt fields in the Estimate attribute formula
with delta_days = DAYS_BETWEEN(DATE_ADD(GanttStartDate, duration, "days"), TODAY()):
with sum_from_today = delta_days>0 AND !DEFINED(ActEnd):
with ms = delta_days*8*60*60*1000:
IF(sum_from_today > 0; RemainingEstimate+ms; TimeSpent+RemainingEstimate)
but I'm getting this error:
Invalid attribute specification, please ensure that correct 'id' and 'format' properties are specified.
If I try the same formula in a column structure, it works perfectly ( I have tried to just create a column in the structure, but after isn't usable as Estimate ).
Any idea?
PS: what I'm trying to do here is to have an estimate that is dynamic and, if a task end is estimated to be before today, it adds up the delta from today and the planned end.
Thanks,
Antonio