I tried doing a simple prototype using Roadmaps, but I can't get it to work. Here's what I did:
1. Create Scrum Project.
2. Create Release 1.0 start today (4/12) and ends one month from today (5/12).
3. Create 4 epics each with 40 hrs (1 week) estimate, assigned to 1 user, with fix version 1.0.
4. If I go to Roadmap I see all 4 epics listed but the calendar is empty.

How do I get this Roadmap to automatically show the estimates for each epic (one after the other since they all have the same assignee) so I can compare the projected delivery based on estimates vs Release's original expected delivery date?