I started a new project to track go-to-market tasks. We are in Jira in the cloud.
If I set the issues as tasks, they cannot have dates set against them so we can use the roadmap as a gantt chart, but they do show up in the sprint board.
If I set the issues as epics, we can set dates for them and use the roadmap, but they do not show up in the sprint board.
Is there a way to make both occur? I want all the issues in the sprint to show up in the roadmap and in the sprint board.