i accidently started a new sprint before closing the old sprint. Now i have stories in the new sprint that should be in the old sprint and are marked as complete. How do i move the stories to my past sprint?
classic project? see if you can edit the Sprint field on these issues and remove them from the new sprint but leave in the old one then complete the old sprint.
thank you for the quick response ... it only allows me to go forward not backwards.
i thought you indicated you had the old sprint still active.