Is it possible that the subtasks are scored and showing in burndown graphic? Exemplo: I have a history task and i need assign points for subtask associate with them and I want that is showed in burndown when I finish the subtaks.
Burndown does not measure sub-tasks, as you do not commit to doing them in a sprint, you commit to their parents.
So, no, you won't get sub-tasks scored, estimated or burned down on.