Hello,
The burndown graph of my project did not generate the gray line that defines the expected speed of completion of tasks.
How can I solve this?
tks
Marcelo
Hello @Marcelo Piveta -- Welcome to the Atlassian Community!
Would you please post images of your burndown and burnup charts?
Often a cause of no trend line is starting the sprint before any issues have been added. Is that the case?
Best regards,
Bill
Thank you Bill
Maybe
In that case what should I do?
Yes, that appears to be the issue. The gray line is flat on the x-axis because there were no issues in the sprint at the start, so the trend never starts above zero.
This is the intended behavior, as opposed to other burn-chart designs which reset the trend line if the scope changes.
__Bill