JIRAのプロジェクトの1日の稼働時間をデフォルト8時間から7.5時間に変更したいのですが、変更方法ご存じでしょうか?
Hi @aranami katsuhisa ,
System admin can modify Working hours per dayin Global time tracking settings.
Hi @Ollie Guan
Thanks for your very quick answer.Is that possible only by Global Admin ??And if that is , does it affect all project ??
Unfortunately, this is a global configuration, you cannot set different schemes for a single project.
@Ollie Guan Very thanks for your answer.I will consider best way for my project and the others as well.