Hi,
I created a new project in which I forgot to use our customized issue screen, so it took the default screen. The start date was set to 06/17/20, even though I created the task in October 12th 2020.
I then switched to the customized issue screen in which I have the "due date" as one of the fields. I then tried to update both fields (start date to a particular day last week in the due date a date at the end of this week), but after a few seconds the dates are reverted back to 06/17/20 (even before I refresh the page).
There are no dependencies on these issues, so I really don't have a clue why this is happening. Any help would be appreciated. If you need any additional info, please let me know.
Thanks!
/Art