So i want to set custom velocity for future sprints. Right now, if I set 30pts velocity for my team it's set on all the sprints.
You don't get to set a velocity because you would be telling lies. Velocity is calculated from data about what has happened, it's not something you guess at.
OK. But what if it's the first pi planning and you have to plan for 4 sprints ahead? Like a simulation
Do you know if there's a tutorial about capacity allocation on future sprints ? I looked everywhere but couldn't find one.
Does advanced roadmaps compute velocity ?